Construction Progress Update
The Penny
November 2026
Move-In Targeted August 1, 2027
Updated · 415 College Main St, College Station, TX 77840
When does The Penny open? As of November 19, 2026, the construction schedule targets the certificate of occupancy for April 2027 and resident move-in for August 1, 2027. The Penny has topped out, the roof is complete, every window is installed, and interior finishes are underway on Level 9. Full dry-in is targeted for mid-January 2027.
Where We Are
Next stop: a fully sealed building
The foundation is complete and The Penny has topped out, meaning the structure has reached its full height. The next milestone is dry-in, the point when the roof, walls, and windows seal the building against weather. With the construction hoist targeted to come down in late December, full dry-in is targeted for mid-January 2027.
- ✓CompleteFoundation
- ✓CompleteTopped Out
- Mid-Jan 2027Dry-In
- Through Mar 2027Interior Finishes
- Early 2027Amenities & Site Work
- Apr 2027Certificate of Occupancy
- Aug 1, 2027Move-In
Rendering to Reality
Interiors are coming to life!

The pool, fitness center, and courtyard are all under construction, and the pool is targeted for completion between now and January. When it is done, this deck will look like the rendering: a pool with a hot tub and cold plunge, a sundeck, and a 137-inch outdoor TV.
This Month at The Penny
Closing in, finishing out
Exterior Facade
All windows are installed. Crews are finishing the remaining exterior work around the hoist area, targeted for completion by the end of December. Storefront work at the courtyard and gym continues.
✓ Roof
The roof is complete. Related work continues until the rooftop units, the building's heating and cooling equipment, are installed near the end of November.
Interiors
Painting is underway on Level 9, with Level 10 scheduled to start the following week. Cabinets are going in on Level 9 and drywall continues. Flooring is scheduled to begin in November on Level 1 and work its way up.
Building Systems
Electrical, plumbing, HVAC, and fire sprinkler rough-ins are complete. Trim work, the installation of final fixtures and devices, is ongoing.
Amenities
Work continues on the pool, fitness center, and courtyard. Amenity areas and townhomes are targeted for completion in November or early December.
Site Work
Site work is ongoing, with amenity and site work targeted to finish in early 2027.
Looking Ahead
The building closes up this winter
November 2026
- Rooftop units installed near month end
- Flooring begins on Level 1
- Painting continues on Level 10
- Amenity areas and townhomes targeted for completion (November to early December)
December 2026
- Construction hoist removed late in the month
- Remaining exterior work around the hoist area targeted for completion
- Pool targeted for completion by January
Early 2027
- Full dry-in targeted for mid-January
- Interior finishes continue through March
- Amenities and site work targeted to finish
- Certificate of occupancy targeted for April
Once the hoist comes down and the last exterior section is closed, the building is sealed and weather can no longer slow the work inside. From there, finishes move floor by floor until the city's certificate of occupancy, targeted for April 2027, ahead of move-in on August 1, 2027.
The Full Picture
Where The Penny stands today
This is the first monthly construction update for The Penny. Today the structure is at full height, the roof is complete, every window is installed, and the electrical, plumbing, HVAC, and fire sprinkler rough-ins are done. Finishes have reached the residential floors, with paint and cabinets underway on Level 9.
This fall's work is about closing in and finishing out. Rooftop units arrive in November, the hoist comes down in December, and the building is targeted to be fully dried in by mid-January. The current schedule targets the certificate of occupancy for April 2027 and resident move-in for August 1, 2027.
Who's Building The Penny
The team behind every floor
Each month the construction team reports progress against the schedule, and this page turns that report into plain language. The Penny is developed by Pinecrest and will be managed by Coastal Ridge Real Estate.
-->Construction terms explained
- Topping out
- Topping out is the point when a building's structure reaches its full height.
- Dry-in
- Dry-in is the stage when a building's roof, walls, and windows are sealed so weather can no longer stop interior work.
- Construction hoist
- A construction hoist is a temporary elevator on the outside of a building that carries crews and materials; removing it lets crews close the last section of the exterior.
- Rough-in
- Rough-in is the stage when electrical wiring, plumbing lines, ductwork, and sprinkler piping are run inside the walls and ceilings before drywall closes them in.
- Trim work
- Trim work is the final installation of visible fixtures and devices, such as outlets, switches, light fixtures, and plumbing fixtures, after rough-in is complete.
- Rooftop units
- Rooftop units are the heating and cooling equipment installed on a building's roof.
- Certificate of occupancy (CO)
- A certificate of occupancy is the local government approval that a building is ready to be lived in.
Frequently asked questions
When will The Penny open?
Resident move-in at The Penny is targeted for August 1, 2027, following a certificate of occupancy targeted for April 2027.
Where does The Penny construction schedule stand?
As of October 27, 2026, the construction schedule targets the certificate of occupancy for April 2027 and resident move-in for August 1, 2027. The foundation is complete, the building has topped out, and the roof is complete.
What happens next in construction?
Rooftop units are targeted for installation near the end of November, flooring is scheduled to begin on Level 1 in November, and the construction hoist is targeted for removal in late December. Full dry-in is targeted for mid-January 2027.
What is dry-in?
Dry-in is the stage when a building's roof, walls, and windows are sealed so weather can no longer stop interior work. At The Penny, full dry-in is targeted for mid-January 2027.
Who is developing The Penny?
The Penny is developed by Pinecrest and will be managed by Coastal Ridge Real Estate.
Where is The Penny located?
The Penny is at 415 College Main St, College Station, TX 77840, in the Northgate District near Texas A&M University and Blinn College's Bryan Campus.
How often is this page updated?
This page is updated monthly with the latest progress from the construction team.
How can I lease at The Penny?
Leasing is open now. Schedule a tour of the leasing office at 1025 University Dr, Suite 106, College Station, or view floor plans at livethepenny.com/floor-plans.
Follow the build
Tour the leasing office at 1025 University Dr, Suite 106, and see the floor plans before The Penny opens.
Schedule a Tour View Floor PlansGet progress photos between updates on Instagram @livethepenny.
The Penny is at full height with the roof done, every window in, and finishes underway on the residential floors. Check back in November to see the rooftop units go in, flooring start on the lower levels, and finishes climb past Level 10.
Construction dates are targets based on the general contractor's current schedule and may change. Renderings are artist's concepts; finishes and features may vary.